Concrete8 min read2025-10-31

How Much Concrete Do I Need? Complete Calculation Guide

Industry-standard concrete calculations for slabs, driveways, footings, and posts. Includes ACI specifications, bag yields, and ready-mix comparisons.

💡
Quick Answer

For a standard 4-inch thick slab, you need 1.23 cubic yards of concrete per 100 square feet. An 80-pound bag yields 0.60 cubic feet, requiring 45 bags per cubic yard.

📊 Concrete Volume by Project Type

Standard Slab (4")

Coverage:81 sq ft/yard
Bags needed:45 (80 lb) per yard
Formula: (L × W × 0.33) ÷ 27 = cubic yards

Driveway (6")

Coverage:54 sq ft/yard
IRC minimum:4-5 inches (6" for RV/heavy trucks)
Formula: (L × W × 0.5) ÷ 27 = cubic yards

Footings (12" deep)

Coverage:27 sq ft/yard
IBC standard:12" below soil
Formula: (L × W × 1.0) ÷ 27 = cubic yards

Posts (12" diameter)

Per foot depth:0.785 cubic feet
Per 4' pier:0.116 yards (5.2 bags)
Formula: (π × r² × h) ÷ 27 = cubic yards

📐 Industry Standard Specifications

Bag Yields (ASTM C150)

Bag SizeCubic FeetBags per Yard
80 lb bag0.60 cubic feet45 bags
60 lb bag0.45 cubic feet60 bags
Cubic yard27 cubic feet

Thickness Requirements (IBC/IRC)

Residential Applications

  • Patios/Walkways: 3.5 inches minimum (4" standard)
  • Garage floors: 4-5 inches (6-8" for heavy vehicles)
  • Driveways: 6 inches minimum
  • Foundation walls: 6-8 inches

Footing Depth

  • Frost zones: Below local frost depth
  • Non-frost areas: 12 inches minimum
  • Always verify with local building department

⚠️Waste Factors (ACI 301)

Slabs
5-8%
Footings
10-15%
Walls
7-10%
Stairs
10-12%

🧮 Step-by-Step Calculation

Example: 10' × 20' Patio Slab (4 inches thick)

1
Calculate cubic feet
10 ft × 20 ft × 0.33 ft = 66 cubic feet
2
Convert to cubic yards
66 ÷ 27 = 2.44 cubic yards
3
Add waste factor (8% for slab)
2.44 × 1.08 = 2.64 cubic yards
4
Calculate bags needed (using 80 lb bags)
2.64 × 45 = 119 bags
Order amount
Round up: 120 bags OR order 3 cubic yards ready-mix

🚛 Ready-Mix vs. Bagged Concrete

Ready-Mix Concrete

Delivered by truck

When to use:

  • Projects requiring 1+ cubic yards
  • Large slabs, driveways, foundations
  • Any project over 50 bags

Advantages:

  • • Professionally mixed to specifications
  • • Consistent strength throughout
  • • Faster pour for large projects
  • • Cost-effective over 1 yard
Typical pricing:
$125-175 per yard
Includes delivery • 1 yard minimum

Bagged Concrete

Mix-on-site

When to use:

  • Small repairs under 1 cubic yard
  • Post holes, small footings
  • Multiple pours over time

Advantages:

  • • Mix only what you need
  • • No minimum order
  • • Store unused bags
  • • Better for small projects
Typical pricing:
$4-6 per 80 lb bag
No minimum • Available at most stores
Note: Mixing 45+ bags by hand is extremely labor-intensive

📋 Common Concrete Projects

10' × 10' Patio (4 inches)

Cubic yards:1.23 yards
80 lb bags:55 bags
Order 1.5 yards ready-mix

Two-car Driveway 20' × 20' (6 inches)

Cubic yards:7.4 yards
Requires 6-inch minimum for vehicle traffic
Order 8 yards ready-mix

50-foot Sidewalk (4' wide, 4 inches thick)

Cubic yards:2.47 yards
80 lb bags:111 bags
Order 2.75 yards ready-mix

Four 12-inch Diameter Deck Posts (4 feet deep)

Cubic yards:0.47 yards
80 lb bags:21 bags
Bagged concrete practical

💪 Concrete Strength Specifications

PSI Ratings (ACI 318)

2,500
PSI
Residential footings, patios
3,000
PSI
Residential slabs, driveways
(Most common)
3,500
PSI
Floors with heavy loads
4,000
PSI
Commercial, high-traffic areas
Standard residential mix: 3,000 PSI with 5-6 inch slump

👷 Professional Standards

🕐Curing Requirements (ACI 308)

  • 7
    Minimum 7 days moist curing for full strength
  • 24
    Avoid foot traffic for 24 hours
  • Full weight-bearing after 7 days
  • 28
    Maximum strength achieved at 28 days

🌡️Temperature Requirements

Minimum pour temp40°F
Maximum pour temp95°F
❄️Cold weather - Concrete must be minimum 65°F during mixing (ACI 306): Use heated mix and insulating blankets
☀️Hot weather (>85°F): Use retarders, shade, and fog misting

📚 Building Code References

ACI 318: Structural Concrete Code
ACI 301: Concrete Specifications
ACI 308: Curing Requirements
IRC R506: Concrete Floor Requirements
IBC 1905: Concrete Construction Standards
ASTM C150: Portland Cement Specifications
Always verify local requirements with your building department. Frost depths, seismic zones, and soil conditions affect specifications.